Formulas & Math


24 words 0 ignored

Ready to learn       Ready to review

Ignore words

Check the boxes below to ignore/unignore words, then click save at the bottom. Ignored words will never appear in any learning session.

All None

Ignore?
CV
=EV-AC
SV
=EV-PV
CPI
=EV/AC
SPI
=EV/PV
EAC
=AC+ETC (when past assumptions are incorrect)
EAC
=(AC+BAC)-EV (when variances aren't typical)
EAC
=BAC/cumulative CPI (when expecting to continue same performance)
EAC
=AC+((BAC-EV)/CPI) [when variances are expected to remain the same]
ETC
=EAC-AC
VAC
=BAC-EAC
TCPI
=Work Remaining/Budget Remaining
communication channels
=N(N-1)/2
present value
=FV/(1+r)^n
future value
=PV(1+r)^n
PERT
=(P+4M+O)/6
six sigma
3.4 defects per million opportunities (DPMO)
six sigma
99.99966%
five sigma
99.977%
four sigma
99.38%
three sigma
93.3%
two sigma
69%
one sigma
31%
PV
budgeted cost of the work performed
AC
actual cost of the work performed